PROJECT: DRAGON INDUSTRIES, Division of Modern USA

Click image for a larger view.
Location: Lamar, CO
Size: 86,000 square feet
Roof Construction: Steel bean and bar joist
Clearance before lifting: 24 feet
Clearance after lifting: 40 feet
 
 

Summary:


Dragon Industries, a major manufacturer of energy products, needed to lift the roof of an existing facility in order to manufacture wind turbine towers. The required clearance under the steel trusses needed to be 40 feet. The existing height of the russes was 24 feet. The lift included the change of existing columns for a 140' x 160' clear span section. The lift made the use of the existing building more advantageous to new manufacturing needs.